Traffic flow improved with police enforcement, heavy-vehicle curbs, but bottlenecks remained due to patchy repairs and narrow stretches.
BENGALURU: For 40,000 schoolchildren and their parents, the school commute to and fro through east Bengaluru is no longer a commute. Children spent nearly 53 school days on roads It is becoming a big part of their school day.

A recent mobility study by Inventure Academy of 42 schools along the state highway-35 corridor revealed that the average school-bus travel time has increased to 112 minutes in 2026-27 from 92 minutes in 2024-25. That adds up to about 374 hours on the road in a 200-day school year – or nearly 53 school days spent on the road. Buses took 2.5 hours for just four kilometres 92 minutes to 112 minutes The numbers illustrate how rapidly the situation has spiraled. Average daily bus commute has increased by about 22% in two academic years. GPS data from 61 school buses shows that average speeds on the corridor dipped to 9.2kmph, with some patches recording as low as 6.4 kmph. In September, school buses took up to 2.5 hours to cover just 4km on the Varthur-Gunjur stretch, leaving students late for exams. Parents have reported buses taking over two hours to travel just a few kilometers, while the study found about 60 per cent of school-bus trips do not arrive at their destinations on time. The SH-35 corridor itself has been identified as a heavily congested arterial and road widening and an elevated corridor has been planned to alleviate some of the bottlenecks. Varthur elevated corridor construction started in May 2019. It was to be completed by November 2021. The study pegged the project at roughly 12% complete, highlighting the gap between the planned infrastructure of the corridor and the reality for commuters today. The city’s Blue Line expansion and other Metro projects are under way, but much of the daily school commute along SH-35 remains reliant on roads and school buses.
KRDCL has now set December 2026 as the latest target for the completion of the Rs 488-crore project after delays due to land acquisition, right-of-way issues, utility shifting, approvals and execution. A later ground report found that traffic flow was better with police enforcement and restrictions on heavy vehicles, but there were still bottlenecks due to patchy repairs and narrow stretches. On the worst days, the situation is even worse. How traffic crisis is eating into students’ school time The problem is especially severe during school hours when multiple choke points happen at the same time. The evening return leg is often worse, with afternoon speeds decreasing. East Bengaluru outran its roads Bengaluru’s growth story is also the story of traffic crisis. Rapid growth in housing, schools and employment have been seen in areas like Varthur, Gunjur, Dommasandra, Whitefield and nearby places in the technology corridor. But the capacity of the roads and their supporting infrastructure have not kept pace. The ongoing project plans to widen parts of the road considerably but land acquisition, utility diversion and delays in execution have slowed the work. The overpass was meant to be part of the solution This is where the infrastructure timeline is hard to ignore. Seven years later, the project is still not at the finish line. Why Metro cannot solve this particular problem alone The Varthur traffic story also has a bigger lesson: Bengaluru’s mobility problem cannot be solved by one infrastructure project. A Metro network can move masses of commuters but it cannot clear the bottlenecks around schools, junctions and incomplete roads. The quick fix The recent reaction suggests that some relief need not wait until the completion of a major project. In the aftermath of the traffic outrage, Bengaluru development minister Krishna Byre Gowda has asked officials to prioritize pothole repairs and address delays in road works. Restrictions on heavy vehicles during school hours have also been imposed by authorities.
Earlier, residents of Varthur had argued that mass transit including Metro connectivity would be a better option for the ever-growing population than just a flyover. The Varthur-Gunjur-Dommasandra corridor is a mix of schools, residential layouts, IT offices and construction activity, which brings thousands of vehicles on to roads not meant for today’s volumes.


So the 53-day number is more than a stunning statistic. For the children who travel through Varthur, Gunjur and Dommasandra the cost is not just in minutes lost in traffic, but in time taken away from school, play, rest and family. You Can Also Check: Gold Rate in Bengaluru | Silver Rate in Bengaluru | Bank Holidays in Bengaluru | Public Holidays in Bengaluru | Bengaluru AQI | Weather in Bengaluru | Petrol Price in Bengaluru | Diesel Price in Bengaluru | CNG Price in Bengaluru | LPG Price in Bengaluru Stay updated with the latest Bengaluru news.
It illustrates the effect of a city’s residential and employment growth outpacing its transport infrastructure. Download the TOI App.
The bigger question for Bengaluru is if its next phase of growth is delivered with infrastructure before the traffic crisis hits the next generation.