Civic officials said asphalting was originally planned for May: The wider industry impact

Civic officials said asphalting was originally planned for May: The wider industry impact

Amrutdham to Tarwala junction road in the city is to be developed ahead of Kumbh Mela

“We have set a target of Dec 2026 for completion of most white-topping works in the city. You Can Also Check: Gold Rate in Nashik | Silver Rate in Nashik | Bank Holidays in Nashik | Public Holidays in Nashik | Petrol Price in Nashik | Diesel Price in Nashik | CNG Price in Nashik | LPG Price in Nashik Stay updated with the latest Nashik news.

Nashik Municipal Corporation (NMC) commissioner Manisha Khatri said white-topping has already started on stretches where utility shifting and underground infrastructure works have been completed. Only one or two stretches may require an additional month or two,” Khatri told TOI . At present, road-widening works are underway on several stretches before the commencement of resurfacing,” she said. Civic officials said asphalting was originally planned for May and June, but had to be deferred as road resurfacing cannot be undertaken during the monsoon. Officials said the IIT inspection is part of NMC’s multi-layered quality assurance mechanism that includes internal monitoring, project management consultants, third-party audits and reviews by independent technical institutions.

“Traffic diversions will have to be managed carefully during the asphalting works. Download the TOI App.

The road upgrade programme suffered delays earlier this year after disruptions in bitumen supply linked to geopolitical tensions in West Asia affected procurement schedules.

Nashik: With less than six months left before the March 2027 deadline for key Kumbh infrastructure works, the civic body will begin asphalting major Kumbh roads from Oct while targeting completion of most white-topping projects by Dec-end.

The Nashik-Trimbakeshwar Kumbh Mela Authority (NTKMA) has approved 32 major road projects worth over Rs 1,350 crore to improve connectivity for the massive influx of pilgrims expected in 2027. Around 66,000 tonnes of the material will be required for Kumbh-related road projects across the city.

Preliminary observations found the works to be broadly in line with prescribed technical standards, according to civic officials. Of these, nearly half are being upgraded through cement concrete white-topping while the remaining roads will be widened and resurfaced with asphalt. The next phase will see large-scale asphalting works begin soon after the monsoon. To avoid further setbacks, NMC has approached petroleum companies through state govt to ensure uninterrupted supply of bitumen. The road network forms a critical part of the broader Kumbh infrastructure push aimed at handling millions of pilgrims travelling between Nashik city, Trimbakeshwar and major transit hubs. Meanwhile, an expert team from IIT-Bombay has carried out an independent quality audit of ongoing concrete road works. The team inspected three major projects, including stretches on Trimbak Road and the Garware-to-XLO point corridor, conducting core-cut tests to assess concrete thickness and construction quality. The experts also reviewed issues related to stormwater drainage, monsoon-related challenges and traffic management during construction.