Dakshina Kannada MP Captain Brijesh Chowta chairs a DISHA meeting in Mangaluru Saturday
Mangaluru: Deputy commissioner Darshan HV said 68% of the waterfront project had been completed. The project was delayed as port land had been leased for 30 years. Officials said around 80% of the work on the road connecting Sultan Bathery and Tannirbhavi had been completed and the road was expected to be ready by Dec. DIC joint director Gokuldas Nayak said 48 developed sites were ready for allotment. So far, 16 applications have been received. Zilla panchayat CEO Narwade Vinayak Karbhari said 968 works had been taken up under MGNREGS. Under the Viksit Bharat–Guarantee for Rozgar and Ajeevika Mission (Gramin), 18,000 works are planned, including 9,000 in horticulture. The target is to generate 15 lakh person-days, but progress has been affected by technical issues. ITDP officer Basavaraju said 1,135 families had been mapped under PM-JANMAN. Applications of 165 beneficiaries had been processed, while 124 were awaiting approval. PWD officials said they had prepared a Rs 23-crore proposal to upgrade a rajakaluve from the runway to the PWD road.
Stay updated with the latest Mangaluru news.
Encroachments on the land need clearing soon, he said. Chowta said he would inspect the park with the DC in the first week of Oct. Chowta said a BC Road-Surathkal bypass was being planned and that the DPR was in the final stage.
He was speaking at the District Development Coordination and Monitoring Committee (DISHA) meeting chaired by Dakshina Kannada MP Capt Brijesh Chowta. Works at the Plastic Park are expected to be completed by the end of Sept. Road works and asphalting are under way, while street lighting, drainage and treatment plant works have been completed. Flooring, painting and installation of windows at the administrative building of the Central Institute of Petrochemicals Engineering and Technology are pending. Additional workers will be deployed to expedite the work. If all works were completed, it would be inaugurated by the end of Oct. A screening committee is expected to meet in Sept to consider the allotments. Chowta directed officials to prepare an action plan to construct houses for eligible Koraga families. Railway officials were also asked to study the feasibility of a station near Mangaluru International Airport. Moodubidire MLA Umanath Kotian raised the issue of waterlogging in the airport area. An estimate is pending for the section within Bajpe Town Panchayat limits. Download the TOI App.

